Question: Determine the probability that the project will be completed in 50 weeks or less. The details of the project are given in the below table
Determine the probability that the project will be completed in 50 weeks or less. The details of the project are given in the below table Variance Pach Activity A Mean 0 B 18 0.25 C 26 011 D 16 0.69 E