Question: Determine the project's duration if the time for activity C is 4 , for activity D is 8 , and for activity F is 3
Determine the project's duration if the time for activity C is 4 , for activity D is 8 , and for activity F is 3 . All activity times are in weeks. a. 19 b. 20 c. 17 d. 23