Question: determines the early start and early finish dates for each 8. (1 point) In critical path analysis, a activity (select the best answer) a. backward

determines the early start and early finish dates for each 8. (1 point) In critical path analysis, a activity (select the best answer) a. backward pass b. late start date c. forward pass d. late finish date