Question: Determining standard time for a task (or job). A work measurement study was carried out in a firm for 10 hours and the following information

Determining standard time for a task (or job). A work measurement study was carried out in a firm for 10 hours and the following information was gen- erated : Units produced 350 Idle time 15 per cent Performance rating 120 per cent 10% of standard time. Allowance time What was the standard time for the task