Question: Determining the earliest start time ( ES ) and earliest finish time ( EF ) for each activity is known as the _ through the

Determining the earliest start time (ES) and earliest finish time (EF) for each activity is known as the _through the network.
A. forward pass
B. crashing
C. backward pass
D. slacking
 Determining the earliest start time (ES) and earliest finish time (EF)