Question: Determining the earliest start time (ES) and earliest finish time (EF) for each activity is known as the _______________ through the network. A.crashing B.forward pass
Determining the earliest start time (ES) and earliest finish time (EF) for each activity is known as the _______________ through the network.
A.crashing
B.forward pass
C.slacking
D.backward pass