Question: Determining the earliest start time (ES) and earliest finish time (EF) for each activity is known as the _______________ through the network. A.crashing B.forward pass

Determining the earliest start time (ES) and earliest finish time (EF) for each activity is known as the _______________ through the network.

A.crashing

B.forward pass

C.slacking

D.backward pass