Question: Determining the Project Schedule Perform a Critical Path Analysis Activity A B C DEFGH Description Build internal components Modify roof and floor Construct collection stack

Determining the Project Schedule Perform a Critical Path Analysis Activity A B C DEFGH Description Build internal components Modify roof and floor Construct collection stack Pour concrete and install frame Build high-temperature burner Install pollution control system Install air pollution device Inspect and test Total Time (weeks) Time (weeks) 2324 4 3 52 25
 Determining the Project Schedule Perform a Critical Path Analysis Activity A

Determining the Project schedule Perform a Critical Path Analysis