Question: Develop a crashing schedule. ACTIVITY NORMAL TIME CRASH TIME COST PER DAY TO CASH a 7 4 $100 b 5 2 $200 6 6 d

Develop a crashing schedule. ACTIVITY NORMAL TIME

Develop a crashing schedule. ACTIVITY NORMAL TIME CRASH TIME COST PER DAY TO CASH a 7 4 $100 b 5 2 $200 6 6 d 8 5 $300 e 7 7 f 7 6 $150 g 3 1 $500 Project costs are $650 per day. 6 7 3 C a g b 5 f f 8