Question: Develop a Gantt Chart based on below table On the same Gantt chart, use a legend to show the project plan and the (actual) project

  1. Develop a Gantt Chart based on below table
  2. On the same Gantt chart, use a legend to show the project plan and the (actual) project progress.
  3. Discuss the significance of the two paths or what they mean to the project.

TABLE 12.15

Activity Immediate predecessors Normal time Budget Organizational unit Percent complete Money spent
A 4 $90 U1 100 $110
B A 2 $35 U2 100 $20
C A 6 $75 U2 40 $40
D B 3 $60 U1 80 $90
E C 10 $80 U1 0 0
F 2 $40 U2 100 $40
G F 5 $55 U1 50 $30
H F 7 $80 U2 100 $60
I D, E, G 1 $40 U2 0 0
J H 10 $100 U1 0 0

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!