Question: Develop a Gantt Chart based on Table below. On the same Gantt chart, use a legend to show the project plan and the (actual) project

  1. Develop a Gantt Chart based on Table below.
  2. On the same Gantt chart, use a legend to show the project plan and the (actual) project progress.
  3. Discuss the significance of the two paths or what they mean to the project.
Activity immediate predecessors normal time budget organizational unit percent complete
A - 4 $90 U1 100
B A 2 $35 U2 100
C A 6 $75 U2 40
D B 3 $60 U1 80
E C 10 $80 U1 0
F - 2 $40 U2 100
G F 5 $55 U1 50
H F 7 $80 U2 100
I D,E,G 1 $40 U2 0
J H 10 $100 U1 0