Question: Develop a Gantt Chart based on Table below. On the same Gantt chart, use a legend to show the project plan and the (actual) project
- Develop a Gantt Chart based on Table below.
- On the same Gantt chart, use a legend to show the project plan and the (actual) project progress.
- Discuss the significance of the two paths or what they mean to the project.
| Activity | immediate predecessors | normal time | budget | organizational unit | percent complete |
| A | - | 4 | $90 | U1 | 100 |
| B | A | 2 | $35 | U2 | 100 |
| C | A | 6 | $75 | U2 | 40 |
| D | B | 3 | $60 | U1 | 80 |
| E | C | 10 | $80 | U1 | 0 |
| F | - | 2 | $40 | U2 | 100 |
| G | F | 5 | $55 | U1 | 50 |
| H | F | 7 | $80 | U2 | 100 |
| I | D,E,G | 1 | $40 | U2 | 0 |
| J | H | 10 | $100 | U1 | 0 |