Question: The performance of a project was evaluated 10 weeks after its start. Refer to Table Activity Immediate predecessors Normal time Budget Organizational unit Percent complete

The performance of a project was evaluated 10 weeks after its start. Refer to Table

Activity Immediate predecessors Normal time Budget Organizational unit Percent complete Money spent
A 4 $90 U1 100 $110
B A 2 $35 U2 100 $20
C A 6 $75 U2 40 $40
D B 3 $60 U1 80 $90
E C 10 $80 U1 0 0
F 2 $40 U2 100 $40
G F 5 $55 U1 50 $30
H F 7 $80 U2 100 $60
I D, E, G 1 $40 U2 0 0
J H 10 $100 U1 0 0
  1. Develop a Gantt Chart based on Table
  2. On the same Gantt chart, use a legend to show the project plan and the (actual) project progress.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!