Question: Develop a process flow chart Use the critical path method to determine the process flow time Answer the questions table [ [ ctivity ,
Develop a process flow chart
Use the critical path method to determine the process flow time
Answer the questions
tablectivityDescription,tableImmediatePredecessorstableActivity Timein weeksAtableSelect administrative and medicalstaffBSelect site and do site survey.,CSelect equipment.,ADtablePrepare final construction plansand layout.BEBring utilities to the site.,BFtableInterview applicants and fillpositions in nursing, support staff,maintenance and security.AGtablePurchase and take delivery ofequipmentCHConstruct the hospital.,DIDevelop an information system.,AJInstall the equipment.,E G HKTrain nurses and support staff.,F I, J