Question: Develop a project charter for the project. Marking Guideline The project title is adequately selected. It is concise and creates a vision for the 1
Develop a project charter for the project.
Marking Guideline
The project title is adequately selected. It is concise and creates a vision for the 1 end result.
Preferably the system approach/project information system approach is to be followed ( PMBK guide or agile project management methodology.
Budget is limited to R500 000
A minimum of five team members must be involved in the running of the project from start to finish.
Project duration must not exceed 10 months,
Additional assumptions and requirements must be adequately added.
The purpose is adequately described.
The description adequately provides a high-level description of the project.
The objective is adequately defined.
The success criteria or expected benefits are adequately presented.
The funding adequately indicates the amount of money the sponsor authorises 3 for the project.
The major deliverables are adequately identified.
The acceptance criteria are adequately described.
The milestone schedule is an adequate list of targets, dates or times for the 4 occurrence of key deliverables.
Adequate and sufficient key assumptions include those that the project rationale or justification is based on.
The constraints and limitations are adequately presented.
The approval requirements adequately define the limits of authority of the 1 project manager.
The overall project charter considers and adequately meets the project 4 requirements and specifications given in the project.
Weighting 40/2 TOTAL
Allocation of Marks 1 2 2 3 2 3 4 1 4 Marking Guideline Required: The following sections are adequately presented in the project charter and are accurately specific to the project. The project title is adequately selected. It is concise and creates a vision for the end result. The purpose is adequately described. The description adequately provides a high-level description of the project. The objective is adequately defined. The success criteria or expected benefits are adequately presented. The funding adequately indicates the amount of money the sponsor authorises for the project. The major deliverables are adequately identified. The acceptance criteria are adequately described. The milestone schedule is an adequate list of targets, dates or times for the occurrence of key deliverables. Adequate and sufficient key assumptions include those that the project rationale or justification is based on. The constraints and limitations are adequately presented. The approval requirements adequately define the limits of authority of the project manager. Approval signature and date adequately indicate that the sponsor has officially or formally authorised the project. The overall project charter considers and adequately meets the project requirements and specifications given in the project. The overall project charter adequately: Provides approval to go forward with the project and commit funding (1); Summarises the key conditions and parameters of the project (1); Establishes the framework for developing a detailed baseline plan for performing the project (1); The format and standard applied are adequate (1). Weighting 4 4 1 1 4 4 40/2Step by Step Solution