Question: Develop a project charter for the project. (20) Marking Guideline Required: The following sections are adequately presented in the Project Charter and are accurately specific
Develop a project charter for the project. (20)
Marking Guideline Required:
The following sections are adequately presented in the Project Charter and are accurately specific to the scenario and the selected focus area:
Allocation of Marks
The project title adequately selected. It is concise and creates a vision for the end result. 1
The purpose adequately summarises the need and justification for the project. 2
The description adequately provides a high-level description of the project. 2
The objective is adequately presented as a statement of what is expected to be accomplished. 3
The success criteria or expected benefits adequately presented an indication of outcomes or quantitative benefits that will result from implementing the project. 2
The funding adequately indicates the total amount of money the sponsor authorises for the project. 3
The major deliverables adequately present the major end products or tangible items that are expected to be produced during and at the completion of the performance of the project. 4
The acceptance criteria are adequately described. 1
The milestone schedule is an adequate list of target dates or times for the occurrence of key events in the project timetable. 4
Adequate and sufficient key assumptions include that project rationale or justification is based on. 4
The constraints are presented to include the main limitations that limit the actions of the project team. 4
The approval requirements adequately define the limits of authority of the project manager. 1 Approval signature and date adequately indicate that the sponsor has officially or formally authorised the project. 1
The overall project charter considers and adequately meets the project requirements and specifications given in the scenario. 4
The overall project charter adequately: Provides approval to go forward with the project and commit the funding (1);
Summarises the key conditions and parameters for the project (1);
Establishes the framework for developing a detailed baseline plan for performing the project (1); The format and standard applied are adequate (1).
4 WEIGHTING 40 2 TOTAL 20