Question: Develop a project schedule. Estimate the resources required for activities. Estimate the duration for an activity. Determine the earliest start and finish times for activities.
Develop a project schedule.
Estimate the resources required for activities.
Estimate the duration for an activity.
Determine the earliest start and finish times for activities.
Determine the latest start and finish times for activities.
Explain and determine total slack.
Identify and explain the critical path.
Discuss the project control process.
Develop updated schedules based on actual progress and changes.
Discuss and apply approaches to control the project schedule.
Prepare a project schedule.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
