Question: Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. ( 7 points ) a . Draw the precedence
Develop a solution for the following line balancing problem,
allowing a cycle time of minutes. points a Draw the
precedence diagram for the set of tasks. b Calculate the
theoretical minimum number of workstations. c Balance this line
using the longest task time heuristic. d What tasks are assigned
to which stations? e Does the solution have the minimum number of
stations? Explain. f How much idle time is there, summed over all
workstations? g What is the efficiency of this line? Work Task
Task Time seconds Task Predecessors A B A C B D
E C D F A G E FN