Question: Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. Draw the precedence diagram for the set of tasks.
Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes.
- Draw the precedence diagram for the set of tasks.
- Calculate the theoretical minimum number of workstations.
- Balance this line by assigning tasks to stations.
- Does the solution have the minimum number of stations? Explain.
- How much idle time is there, summed over all workstations?
- What is the efficiency of this line?
| Work Task | Task Time (seconds) | Task Predecessor(s) |
| A | 70 | - |
| B | 60 | A |
| C | 120 | B |
| D | 60 | - |
| E | 240 | C,D |
| F | 100 | A |
| G | 190 | E,F |