Question: Develop a third sequence using EDD (earliest due date) as a priority rule. Th e plane with the least amount of fl ying time remaining

Develop a third sequence using EDD (earliest due date) as a priority rule. Th e plane with the least amount of fl ying time remaining has the highest priority. Make a Gantt chart showing the landing sequence and evalu-ate the sequence in terms of performance. Calculate mean fl ow time, mean lateness, and average number of planes in the system. Calculate the total cost associ-ated with this sequence (fl ow time multiplied by cost per minute of fl ying time for each fl ight).
\begin{tabular}{cccc} Flight Number & Minutes on Runway & Remaining Flying Time (minutes) & Cost per Minute of Flying Time (\$) \\ \hline 101 & 2.00 & 10 & 100 \\ 118 & 3.00 & 15 & 150 \\ 217 & 2.75 & 8 & 125 \\ 8076 & 1.50 & 5 & 80 \\ 219 & 3.50 & 12 & 200 \\ 894 & 1.75 & 19 & 150 \\ 024 & 2.50 & 16 & 400 \\ 616 & 3.25 & 22 & 300 \end{tabular}Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
