Question: Develop an Activity on Network diagram for the following list of activities. Calculate the ES, EF, LS, LF values as well as Slack time. The

Develop an Activity on Network diagram for the
Develop an Activity on Network diagram for the following list of activities. Calculate the ES, EF, LS, LF values as well as Slack time. The duration unit is weeks Activity Preceding activity Duration none 2. B . 7 C A 6 D . 9 E B,C 7 F 6 G DC 8 3 I E,F,G