Question: Develop and build the following project schedule. MS Project (or any scheduling software) is not to be used Use sticky notes, PowerPoint, Excel, Word, Visio,
Develop and build the following project schedule.
MS Project (or any scheduling software) is not to be used
Use sticky notes, PowerPoint, Excel, Word, Visio, or any drawing-type software

Directions 1. Use the table below to develop a precedence diagram 2. Identify the early start and early finish for each task 3. Identify the late start and late finish for each task 4. Identify the float in each task 5. Identify any tasks that have free float