Develop and build the following project schedule. MS Project (or any scheduling software) is not to be
Fantastic news! We've Found the answer you've been seeking!
Question:
Develop and build the following project schedule.
- MS Project (or any scheduling software) is not to be used
- Use sticky notes, PowerPoint, Excel, Word, Visio, or any drawing-type software
Directions
- Use the table below to develop a precedence diagram
- Identify the early start and early finish for each task
- Identify the late start and late finish for each task
- Identify the float in each task
- Identify any tasks that have free float
Activity | Immediate Preceding Activity | Duration |
---|---|---|
a. Excavate | - | 5 |
b. Foundation | a | 2 |
c. Frame | b | 12 |
d. Electric | c | 9 |
e. Roof | c | 5 |
f. Brick | c | 8 |
g. Finish interior | d | 10 |
h. Finish exterior | d | 7 |
i. Landscape | h | 5 |