Question: Develop and build the following project schedule. MS Project (or any scheduling software) is not to be used Use sticky notes, PowerPoint, Excel, Word, Visio,
Develop and build the following project schedule.
- MS Project (or any scheduling software) is not to be used
- Use sticky notes, PowerPoint, Excel, Word, Visio, or any drawing-type software
Directions
- Use the table below to develop a precedence diagram
- Identify the early start and early finish for each task
- Identify the late start and late finish for each task
- Identify the float in each task
- Identify any tasks that have free float
| Activity | Immediate Preceding Activity | Duration |
|---|---|---|
| a. Excavate | - | 5 |
| b. Foundation | a | 2 |
| c. Frame | b | 12 |
| d. Electric | c | 9 |
| e. Roof | c | 5 |
| f. Brick | c | 8 |
| g. Finish interior | d | 10 |
| h. Finish exterior | d | 7 |
| i. Landscape | h | 5 |
Step by Step Solution
3.33 Rating (147 Votes )
There are 3 Steps involved in it
While I cannot create a visual diagram directly I can provide detailed instructions and a textual re... View full answer