Question: On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV,

On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?

Step by Step Solution

3.48 Rating (168 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

CV EV AC 600 650 50 SV EV PV 600 560 40 CPI EV AC 600 650 92 On day ... View full answer