Question: Develop Input Screens 5 8 gure 2 Design Input & output 33 Problem Definition System Analysis Test System Implement System Develop Output Reports 10 1

Develop Input Screens 5 8 gure 2 Design Input &

Develop Input Screens 5 8 gure 2 Design Input & output 33 Problem Definition System Analysis Test System Implement System Develop Output Reports 10 1 2 2 5 6 Design Database Develop Database 15 2 LS | LFTS Calculate the ES, EF, LS, and LF times and total slack for each activity in the figure 2 above. Activity TED E S EFL 1. Prob. Def. 2. Sys. Analysis 3. Design I/O 4. Design DB 5. Develop Input 6. Develop Output 7. Develop DB 8. Test System 9. Implement