Question: Develop the material requirements plan for component H of the end product A that has the following product structure tree. Lead times for A and
Develop the material requirements plan for component H of the end product A that has the following product structure tree. Lead times for A and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the start of week 8. There are currently 21 units of B and 125 units of E Projected on-hand, and 40 units of H are in production by a supplier and are scheduled to be received by the start of week 2. (Do not leave any empty spaces; input a 0 wherever it is required.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
