Question: Develop the material requirements plan for component H of the end product A that has the following product structure tree. Lead times for A and
Develop the material requirements plan for component H of the end product A that has the following product structure tree. Lead times for A and each component except B are one week. The lead time for B is three weeks. Fifty five units of A are needed at the start of week 8. There are currently 24 units of B and 105 units of E Projected on-hand, and 50 units of H are in production by a supplier and are scheduled to be received by the start of week 2. (Do not leave any empty spaces; input a 0 wherever it is required.)
| Master Schedule | |||||||||||
| Week | Beg. Inv. | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | ||
| Quantity | 55 | ||||||||||