Question: Different from aggregate planning, Master Production Schedule (MPS) shows detailed disaggregation of the aggregate production plan, listing the exact end items to be produced by

Different from aggregate planning, Master Production Schedule (MPS) shows detailed disaggregation of the aggregate production plan, listing the exact end items to be produced by a specific period.