Question: Discuss Project crashing. Using the following example show how calculations are made to know which activity to crash. Example Activity Slope Maximum I.D crash time

Discuss Project crashing. Using the following
Discuss Project crashing. Using the following example show how calculations are made to know which activity to crash. Example Activity Slope Maximum I.D crash time Direct Costs Normal Crash Time Cost Time Cost A S 30 3 5 $ 60 2 $ 150 B 20 2 7 30 5 70 40 1 6 40 5 80 D 25 4 10 25 6 125 E 50 2 8 70 6 170 F 0 0 6 30 6 180 Note the activity Sequences are: A-B-D-F A-C-E-F The Indirect costs are: A = 350 B = 300 C = 275 D = 200 E = 175 F = 150