Use the accompanying template to help complete the following exercises and provide a comprehensive narrative to support your findings:
1. In month 9 the following Project Stallion information is available: Actual cost is $2,000, earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project. What is your assessment of the project on month 9?
2. On day 51 Project Blue has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV and CV for the project. What is your assessment of the project on day 51?