Question: Do a forward and backwards pass to calculate the earliest start (ES), earliest finish (EF), latest start (LS), and latest finish (LF) for each activity

Do a forward and backwards pass to calculate the earliest start (ES), earliest finish (EF), latest start (LS), and latest finish (LF) for each activity in the network picture below. The numbers represent amount of days for that activity. Also, give the expected project completion time and identify the activities that are part of the critical path.