Question: Do an AON diagram for the network given below. Include total float, free float, and the critical path. Activity Duration Predecessor Activity Duration Predecessor A
Do an AON diagram for the network given below. Include total float, free float, and the critical path.
| Activity | Duration | Predecessor |
| Activity | Duration | Predecessor |
| A | 8 | START |
| L | 9 | H,I,J |
| B | 6 | START |
| M | 6 | I,J |
| C | 3 | A |
| N | 3 | K,L |
| D | 6 | A,B |
| O | 5 | L,M |
| E | 4 | B |
| P | 6 | M |
| F | 6 | B |
| Q | 2 | N |
| G | 10 | C |
| R | 4 | O,P |
| H | 7 | C,D,E |
| S | 3 | P,Q |
| I | 5 | D,E |
| T | 6 | Q |
| J | 6 | E,F |
|
|
|
|
| K | 2 | G,H |
| END |
| R,S,T |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts