Question: DO NOT USE MICROSOFT PROJECT PLEASE! 1. (7 pts) The following data was collected for Project Widget at Schuman Works. Data was collected following weeks

DO NOT USE MICROSOFT PROJECT PLEASE!
1. (7 pts) The following data was collected for Project Widget at Schuman Works. Data was collected following weeks 10 and 20. Note: AC= Actual Costs in the table below. This problem should be worked by hand or Excel, not using MSP. a. (3 pts) Calculate EV and PV for each task and the total for the project for each time period. b. (3 pts) Calculate the CV, SV, CPI and SPI, ETC and EAC for the project (don't need each task) at each of those time periods. c. (1 pt) What can you say about the health of the project? (Must discuss the variances here) 2. (3 pts) Rework the information for parts a and b of problem 1 using the 50/50% rule for the percent completion. Any change in the health