Question: Do you think that Lag same as Float? Why? Identify all merged and burst activities. If activity (E) is delayed by (4) days, how is
- Do you think that Lag same as Float? Why?
- Identify all merged and burst activities.
- If activity (E) is delayed by (4) days, how is the project completion time affected?
- Calculate the total resources hours required.
- Prepare a resource loading table
- Balance the demand for resources by resource leveling.
- Note that the project starts on January 1st 2020, five working days a week, 9 hours per/day. Please follow the rules for resource leveling, there might be a faster solution but it will not be considered as the right answer.
| Activity | Duration /Days | Predecessors | Slack | Resources Hours Needed | Total Resources Hours required |
| A | 3 | --- | 2 | ||
| B | 4 | --- | 3 | ||
| C | 5 | --- | 3 | ||
| D | 3 | A | 1 | ||
| E | 5 | A | 2 | ||
| F | 4 | B | 3 | ||
| G | 3 | C | 2 | ||
| H | 4 | C | 1 | ||
| I | 2 | D,E | 3 | ||
| J | 7 | E,F | 2 | ||
| K | 3 | F,G | 2 | ||
| L | 2 | G,H | 2 | ||
| M | 3 | D,I,J, | 4 | ||
| N | 3 | H,K,L | 3 | ||
| O | 5 | M,N | 3 | ||
| Total | |||||