Question: Do you think that Lag same as Float? Why? Identify all merged and burst activities. If activity (E) is delayed by (4) days, how is

  • Do you think that Lag same as Float? Why?
  • Identify all merged and burst activities.
  • If activity (E) is delayed by (4) days, how is the project completion time affected?
  • Calculate the total resources hours required.
  • Prepare a resource loading table
  • Balance the demand for resources by resource leveling.
  • Note that the project starts on January 1st 2020, five working days a week, 9 hours per/day. Please follow the rules for resource leveling, there might be a faster solution but it will not be considered as the right answer.

Activity

Duration

/Days

Predecessors

Slack

Resources Hours Needed

Total Resources Hours required

A

3

---

2

B

4

---

3

C

5

---

3

D

3

A

1

E

5

A

2

F

4

B

3

G

3

C

2

H

4

C

1

I

2

D,E

3

J

7

E,F

2

K

3

F,G

2

L

2

G,H

2

M

3

D,I,J,

4

N

3

H,K,L

3

O

5

M,N

3

Total

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!