Question: Use the table below to answer the following questions: Draw the network diagram. What is the estimated total duration for the project? Identify the critical
Use the table below to answer the following questions:
- Draw the network diagram. What is the estimated total duration for the project?
- Identify the critical path.
- Do you think that Lag same as Float? Why?
- Identify all merged and burst activities.
- If activity (E) is delayed by (4) days, how is the project completion time affected?
- Calculate the total resources hours required.
- Prepare a resource loading table
- Balance the demand for resources by resource leveling.
- Note that the project starts on January 1st 2020, five working days a week, 9 hours per/day. Please follow the rules for resource leveling, there might be a faster solution but it will not be considered as the right answer.
| Activity | Duration /Days | Predecessors | Slack | Resources Hours Needed | Total Resources Hours required |
| A | 3 | --- |
| 2 |
|
| B | 4 | --- |
| 3 |
|
| C | 5 | --- |
| 3 |
|
| D | 3 | A |
| 1 |
|
| E | 5 | A |
| 2 |
|
| F | 4 | B |
| 3 |
|
| G | 3 | C |
| 2 |
|
| H | 4 | C |
| 1 |
|
| I | 2 | D,E |
| 3 |
|
| J | 7 | E,F |
| 2 |
|
| K | 3 | F,G |
| 2 |
|
| L | 2 | G,H |
| 2 |
|
| M | 3 | D,I,J, |
| 4 |
|
| N | 3 | H,K,L |
| 3 |
|
| O | 5 | M,N |
| 3 |
|
| Total |
| ||||
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock