Question: dots 3 . 8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that
dots
Roger Ginde is developing a program in supply chain management certification
for managers. Ginde has listed a number of activities that must be completed
before a training program of this nature could be conducted. The activities,
immediate predecessors, and times appear in the accompanying table:
tableACTIVITYIMMEDIATE PREDECESSORSTIME DAYSABCBEA DGE F
a What is the project length?
b What are the critical activities?
c How much slack is in activity C
d What is the early startearly finish and the late startlate finish for activity F
e What if activity F was delayed by days. What impact would it have on the project and critical path?
tableActivityNorm Time,Crash Time,Crash $Normal $PredecessorsABACBDAEBFGD EHFG
a What is the project length?
b What activities are on the critical path?
c What activity should be crashed first and what is the cost?
d What is the maximum that can be crashed from the project and what is the total cost?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock