Question: Dr. Lori Baker, operations manager at Nesa Electronics, prides herself on excellent assembly-line balancing. She has been told that the firm needs to complete 120
Dr. Lori Baker, operations manager at Nesa Electronics, prides herself on excellent assembly-line balancing. She has been told that the firm needs to complete 120 instruments per 24-hour
day. The assembly-line activities are:
| Task | Performance Time (mins) | Predecessors | Task | Performance Time (mins) | Predecessors | ||
| A | 4 | G | 5 | F | |||
| B | 6 | H | 7 | D, E | |||
| C | 8 | A | I | 2 | H | ||
| D | 7 | A, B | J | 9 | E | ||
| E | 3 | B | K | 1 | G, I, J | ||
| F | 5 | C | |||||