Question: Draw a Critical Path Method that shows EST,EFT,LST,LFT, and slack time. The amount of time to complete is below. Preferably in Excel with formulas. Description
Draw a Critical Path Method that shows EST,EFT,LST,LFT, and slack time. The amount of time to complete is below. Preferably in Excel with formulas.
| Description | |
| Develop Project Plans | |
| Clear site | A |
| Build Foundation | B |
| Install Framing | C |
| Set Roof | D |
| Sheathing | D |
| Electrical | D,E,F |
| Plumbing | D,E |
| Install Roofing | E |
| Windows | F |
| Heating | D,E,F |
| Drywall | F,G,H,I,J,K |
| Interior Finishes | L |
| Exterior Finishes | F |
The amount of time it takes to complete these activities is below
| (days) | |
| Description | Time |
| Develop Project Plans | 120 |
| Clear Site | 30 |
| Build Foundation | 14 |
| Install Framing | 42 |
| Set Roof | 3 |
| Sheathing | 7 |
| Electrical | 7 |
| Plumbing | 7 |
| Install Roofing | 3 |
| Windows | 5 |
| Heating | 10 |
| Drywall | 21 |
| Interior Finishes | 60 |
| Exterior Finishes | 30 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock