Question: Draw a Critical Path Method that shows EST,EFT,LST,LFT, and slack time. The amount of time to complete is below. Preferably in Excel with formulas. Predecessors
Draw a Critical Path Method that shows EST,EFT,LST,LFT, and slack time. The amount of time to complete is below. Preferably in Excel with formulas.
| Predecessors | ||
| Build a House - Task List | ||
| Activity | Description | |
| A | Clear site | |
| B | Build Foundation | A |
| C | Install Framing | B |
| D | Set Roof | C |
| E | Sheathing | C |
| F | Electrical | C,D,E |
| G | Plumbing | C,D |
| H | Install Roofing | D |
| I | Windows | E |
| J | Heating | C,D,E |
| K | Drywall | E,F,G,H,I,J |
| L | Interior Finishes | K |
| M | Exterior Finishes | I |
This is the time it will take to complete each section of building a home
| Activity | Description | Time |
| (days) | ||
| A | Clear Site | 30 |
| B | Build Foundation | 14 |
| C | Install Framing | 42 |
| D | Set Roof | 3 |
| E | Sheathing | 7 |
| F | Electrical | 7 |
| G | Plumbing | 7 |
| H | Install Roofing | 3 |
| I | Windows | 5 |
| J | Heating | 10 |
| K | Drywall | 21 |
| L | Interior Finishes | 60 |
| M | Exterior Finishes | 30 |