Question: Please draw a critical path method that shows ES,EF,LS,LF, and slack time. Preferably in Excel with formulas. This is a different question from the other

Please draw a critical path method that shows ES,EF,LS,LF, and slack time. Preferably in Excel with formulas. This is a different question from the other one I found posted. This goes all the way to S and has different tasks.

CPM Project Management
Build A Home
(days)
Activity Description Predecessors Time
A Develop Project Plans 75
B Clear Site A 5
C Excavation B 3
D Footings C 3
E Foundation C 3
F Curing D,E 7
G Temporary Power D,E 1
H Framing/Rebar F 37
I Set Roof H 2
J Exterior Walls J 2
K Sheathing H,J 4
L Install Roofing K 3
M Pre-Wiring J,L,K 7
N MEP Inspections M 1
O Drywall/Texture H,I,K,L,M 6
P Cabinet/Doors/Interior Paint J,K,C 4
Q Trim/Molding P 1
R Plumber/Electrician/HVAC/Utilities O 7
S Certificate of Occupancy N,R 7

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!