Question: Draw a Network Diagram. Do a forward and backward pass to determine the float in Task E. Task Duration Days Dependency A 3 B 5

Draw a Network Diagram. Do a forward and backward pass to determine the float in Task E. Task Duration Days Dependency A 3 B 5 A C 4 B D 6 B E 7 C F 9 D G 2 F H 4 E, G Group of answer choices 0 days (in critical path) 6 days 8 days 2 days