Question: Draw a network diagram using the Two Pass method to answer the following questions: Activity Estimated time Successor A 4 B, C B 5 E

Draw a network diagram using the Two Pass method to answer the following questions:

Activity

Estimated time

Successor

A

4

B, C

B

5

E

C

6

D

D

3

E

E

10

F, G

F

3

H

G

6

I

H

2

I

I

3

N/A

What is the critical path?

What is the duration of the project?

Which tasks have total float? Which tasks have free float?

Which tasks can you crash in order to complete the project faster?