Question: Draw a PERT OR a Gantt chart and estimate the time it will take to complete the work described below. Also, identify the critical path(s)

 Draw a PERT OR a Gantt chart and estimate the time

Draw a PERT OR a Gantt chart and estimate the time it will take to complete the work described below. Also, identify the critical path(s) of tasks and any possible delay time for the non-critical tasks. (15 points) The design of the information system for the new order processing system of a business involves the following tasks: Task Immediate Expected Predecessor Duration (Days) None 2 A 1 B B 3 D B 2 E D 4 F CD 2 G E 3 . F 3