Question: Draw a PERT OR a Gantt chart and estimate the time it will take to complete the work described below. Also, identify the critical path(s)
Draw a PERT OR a Gantt chart and estimate the time it will take to complete the work described below. Also, identify the critical path(s) of tasks and any possible delay time for the non-critical tasks. (15 points)
The design of the information system for the new order processing system of a business involves the following tasks:
| Task | Immediate Predecessor | Expected Duration (Days) |
| A | None | 2 |
| B | A | 1 |
| C | B | 3 |
| D | B | 2 |
| E | D | 4 |
| F | C, D | 2 |
| G | E | 3 |
| H | F | 3 |