Question: Draw a project network for this project. Calculate EST,EFT,LFT , LST table [ [ Activity , Predecessors,Duration ( days ) ] , [ A:train

Draw a project network for this project.
Calculate EST,EFT,LFT,LST
\table[[Activity,Predecessors,Duration(days)],[A:train workers,-,6],[B:purchase raw materials,-,9],[C:produce product 1,A, B,8],[D:produce product 2,A, B,7],[E:test product 2,D,10],[F:assemble products 1&2,C, E,12]]
 Draw a project network for this project. Calculate EST,EFT,LFT,LST \table[[Activity,Predecessors,Duration(days)],[A:train workers,-,6],[B:purchase