Question: Draw a project network from the following information. What activity(s) is a burst activity? What activity(s) is a merge activity? ID Predecessor A None B
Draw a project network from the following information. What activity(s) is a burst activity? What activity(s) is a merge activity?
| ID | Predecessor |
| A | None |
| B | A |
| C | B |
| D | C |
| E | C |
| F | A |
| G | D,E,F |
| H | G |
What type of activity is each of the activities from A -H? Both burst & merge, Neither burst & merge, burst, merge?