Question: . Draw a Time-Scaled Network from the following data: (10 Marks) Event Activity Duration (days) Preceding activity 1 A 5 2 B 7 A 3
. Draw a Time-Scaled Network from the following data: (10 Marks)
| Event | Activity | Duration (days) | Preceding activity |
| 1 | A | 5 |
|
| 2 | B
| 7 | A |
| 3 | C
| 9 | A |
| 4 | D | 7 | B |
| 5 | E
| 2 | C |
| 6 | F
| 6 | C |
| 7 | G | 2
| D |
| 8 | H
| 3 | G & F |
| 9 | J | 4
| H |
In public projects, describe how financial costs are converted into economic prices and why.
Explain the differences between a project and a business operation.