Question: . Draw a Time-Scaled Network from the following data: (10 Marks) Event Activity Duration (days) Preceding activity 1 A 5 2 B 7 A 3

. Draw a Time-Scaled Network from the following data: (10 Marks)

Event

Activity

Duration (days)

Preceding activity

1

A

5

2

B

7

A

3

C

9

A

4

D

7

B

5

E

2

C

6

F

6

C

7

G

2

D

8

H

3

G & F

9

J

4

H

In public projects, describe how financial costs are converted into economic prices and why.

Explain the differences between a project and a business operation.