Question: Draw an Activity on Arrow diagram. Include the calculations values of the forward pass (earliest dates) and backward pass (latest dates) on the nodes. Identify

Draw an Activity on Arrow diagram. Include the calculations values of the forward pass (earliest dates) and backward pass (latest dates) on the nodes. Identify all the project paths for the diagram and calculate the total float/slack for all the identified paths.
\begin{tabular}{|c|l|c|} \hline Activity & Estimated Duration & Predecessor \\ \hline A & 1 days & \\ \hline B & 2 days & A \\ \hline C & 2 days & B \\ \hline D & 2 days & A \\ \hline E & 3 days & D \\ \hline F & 4 days & B \\ \hline G & 5 days & B \\ \hline H & 6 days & G \\ \hline I & 6 days & C \\ \hline J & 8 days & G \\ \hline K & 5 days & E, F \\ \hline L & 6 day & I, H \\ \hline \end{tabular} Table 1Step by Step Solution