Question: Project Management. Consider the following Precedence Table: Task ID Precedence Normal Duration (Months) Normal Cost ( Millions) Crash Duration (Months) Crash Cost ( Millions) A
Project Management. Consider the following Precedence Table:
| Task ID | Precedence | Normal Duration (Months) | Normal Cost ( Millions) | Crash Duration (Months) | Crash Cost ( Millions) |
| A | - | 3 | 2 | 1 | 4 |
| B | - | 4 | 3 | 1 | 12 |
| C | - | 2 | 2 | 1 | 4 |
| D | C | 1 | 3 | - | - |
| E | A,B,C | 3 | 5 | 2 | 6 |
a. Draw the (Normal) Project Network Diagram
b. What is the minimum project completion time?
c. Identify the critical path
d. Create a Gantt chart for the project, scheduling non-critical tasks as early as possible
Crash the project to 4 months
e. Draw the Project Network Diagram for the crashed project
f. How much does it cost to crash the project 4 months?
g. Identify the critical path for the crashed project