Question: Draw an arrow network that will represent the overlapping relationships between the activities of the following project. After the first 4 0 percent of Activity

Draw an arrow network that will represent the overlapping relationships between the activities of the following project. After the first 40 percent of Activity A has been done, Activity B can be started. Once Activity A is done, 25 percent of the work of Activity C must be remaining. After the first 75 percent of Activity C is completed, 50 percent of Activity D must remain, and Activity D must follow the completion of Activity B.