Question: draw AON diagram Time (days) Immediate Predecessor(s) a m b 8 4 Activity A B D E F G H I J K 3 3
draw AON diagram
Time (days) Immediate Predecessor(s) a m b 8 4 Activity A B D E F G H I J K 3 3 2 1 6 2 6 1 3 10 14 2 6 4 2 7 4 10 2 6 11 16 8 3 8 6 14 4 9 12 20 10 BD A, E A, E F G HI a) Determine the expected completion time and variance for each activity. b) Determine the total project completion time and the critical path for the project. c) Determine ES, EF, LS, LF, and slack for each activity. d) What is the probability that McGee Carpet and Trim will finish the project in 40 days or less? PX