Question: Draw AON network, determine total time for project and draw Gantt chart Activity Predecessor Duration A 5 B 4 C A 3 D A 4

Draw AON network, determine total time for

Draw AON network, determine total time for project and draw Gantt chart Activity Predecessor Duration A 5 B 4 C A 3 D A 4 E A 6 F B,C 4 G D UT . DE 6 F 6 J GH 4 32 % Inl lil IT iii I B A 1